The Cost of Delays: State Street Master Plan

State Street’s aging water, sewer and stormwater systems need renewal. Explore how delaying work could affect costs, starting with the City’s full $96.02 million master-plan estimate for 2027.

Estimated project and disruption cost

$105.8M

If construction starts in 2030. Includes construction, repairs, cleanup and disruption while waiting.

2030
20272037
Annual construction-cost growth

3.3% follows historical construction-cost growth.

Adjust flooding and repairs
Adjust assumptions
Flood-related incident assumptions
$

Count public repair and cleanup costs. Avoid overlapping the emergency-repair allowance.

$
Adjust assumptions
Emergency repair assumptions
$

Include repair, setup, traffic control and temporary restoration once.

$
Illustrative assumptions

Costs incurred due to delays

Above the $96.02M starting estimate
Construction inflationFlood repair and cleanupEmergency repairsBusiness disruption

$9.8M in costs incurred due to delays

Share of delay costs by category, above the $96.02M starting estimate for 2027.

Why timing matters

Beneath State Street, water pipes supply homes and businesses, sewer pipes carry wastewater away, storm drains manage rain, and underground lines deliver electricity, gas and communications. Much of this infrastructure is more than 50 years old, and the City’s master plan identifies systems nearing the end of their service lives.

These aging systems will need repair and renewal regardless of the street’s future design. The question is not if, but when. The master-plan estimate also includes broader street improvements; it is not a price for utility replacement alone.

Sources, assumptions and calculations

The City estimate issued in 2026 is used as the $96.02 million starting cost for construction in 2027, including construction, contingency, engineering and right of way. City estimate, Attachment E.

The 3.3% preset rounds the ENR national 20-city Construction Cost Index’s 2015–2025 annual compound growth of 3.3135%. Other presets show lower or higher price growth. These are scenarios rather than forecasts, and prices can rise beyond any preset. ENR source, page 77 · Original report.

Flood and emergency incident defaults are adjustable scenario assumptions. Saved assumptions · ENR annual history.

Construction costs compound at the selected annual inflation rate from the 2027 baseline. Incident costs also increase with prices during the waiting period.

Each incident combines direct repair or cleanup costs with disruption days multiplied by the daily economic impact. Incident timing is illustrative and changes when the page is refreshed. The same timeline is used across construction dates and assumptions during your visit. Annual rates set the overall number of incidents, with irregular timing between years. Include only losses not counted in another cost.

Included costs and scope

The scenario combines public construction and repair costs with estimated economic disruption. It excludes financing, discounting, disruption during reconstruction itself, and maintenance or incidents after reconstruction. Construction contingency is already included.

2030 · Public cost$105.8M