  "baseline_usd": 96020000,
  "baseline_construction_start": 2027,
  "estimate_issued": 2026,
  "baseline_source": "City of Santa Barbara 2026 estimate, Attachments E and F; estimate assumes a 2027 construction start as clarified by the user.",
  "horizon_years": 10,
  "price_dates": "2027\u20132037",
  "planning_start": 2027,
  "source_price_year": 2027,
  "date_alignment": "The estimate was issued in 2026 for a 2027 start. Construction in 2027 is $96.02M with no extra escalation. Prices and interim costs escalate only after 2027.",
  "chart_axes": {
    "quantity": "Costs incurred due to delays, equal to total minus the $96.02M baseline.",
    "ranges": {
      "0": {
        "viewYears": 0,
        "referenceTotal": 96020000,
        "referenceOverage": 0,
        "delayMin": 0,
        "delayMax": 15000000,
        "barMax": 15000000
      },
      "3": {
        "viewYears": 3,
        "referenceTotal": 117936748.54333547,
        "referenceOverage": 21916748.543335468,
        "delayMin": 0,
        "delayMax": 30000000,
        "barMax": 30000000
      },
      "10": {
        "viewYears": 10,
        "referenceTotal": 178739061.58879742,
        "referenceOverage": 82719061.58879742,
        "delayMin": 0,
        "delayMax": 90000000,
        "barMax": 90000000
      }
    },
    "baseline_project_usd": 96020000,
    "line_baseline_usd": 0,
    "reference_scenario": "5% annual escalation and both default incident scenarios enabled, including economic impacts.",
    "rounding": "Line reference delay cost rounded UP to the next $15M using the session incident schedule, with $15M grid intervals. The lower bar shows component shares across its full width without a dollar axis.",
    "behavior": "The plot always spans 2027\u20132037, with 2030 selected initially. Baseline, three-year and ten-year cards select dates without changing the plot range or scale. Inflation stays visible; incident configuration is collapsed above the plot. Custom incident costs exceeding the reference retain their actual totals and show overflow."
  },
  "default_inputs": {
    "inflationPct": 3.3,
    "delayYears": 3,
    "repairsEnabled": true,
    "repairsPerYear": 2,
    "repairCost": 250000,
    "repairDays": 3,
    "repairEconomicPerDay": 25000,
    "floodsEnabled": true,
    "floodsPerYear": 2,
    "floodCost": 500000,
    "floodDays": 3,
    "floodEconomicPerDay": 50000
  },
  "inflation_presets": [
    {
      "value": 2,
      "label": "Optimistic",
      "detail": "2% annual escalation"
    },
    {
      "value": 3.3,
      "label": "Historical trend",
      "detail": "3.3% annual escalation"
    },
    {
      "value": 5,
      "label": "Higher escalation",
      "detail": "5% annual escalation"
    }
  ],
  "historical_window": "ENR national 20-city CCI published annual averages, 2015\u20132025",
  "historical_anchors": {
    "2015": 10034.0,
    "2025": 13901.0
  },
  "historical_cagr_pct": 3.3135285637218237,
  "formula": "Later construction plus interim repair/flood costs and their economic impacts. Costs incurred due to delays equal total minus $96.02M.",
  "incident_timing": "Illustrative discrete timing, randomized once per browser visit and held fixed across all views and assumptions. Draw round(annual rate * 9) events uniformly across years 1\u201310, excluding the first year. Entered 2027 costs escalate at each occurrence. This is a visual scenario, not a probability forecast. Node builds use a deterministic reference schedule.",
  "cost_coverage": "Same escalation proxy for full project estimate, including existing contingency, engineering and right of way. Incident prices are all-in inputs; do not count the same incident under repairs and flooding.",
  "economic_scope": "Net economic impact per affected day is included automatically for each enabled incident type, separate from direct public repair costs. Do not enter gross sales or impacts already included elsewhere.",
  "excluded": [
    "Financing and discounting",
    "Construction-period disruption",
    "Post-construction maintenance and incidents",
    "Full lifecycle/service-equivalence valuation"
  ],
  "interpretation": "Reconstruction budget priced at its selected start date plus selected pre-construction spending. Exploratory nominal cost, not an official forecast, probability interval, avoided-cost finding or lifecycle comparison. Presets are assumptions; escalation may exceed any preset.",
  "illustrative_inputs": "Emergency and flood amounts/frequencies are editable examples. Both incident scenarios start enabled. Each defaults to 2 incidents/year and 3 disruption days/incident; maximum frequencies are 4 repairs/year and 5 floods/year. Economic impacts are always included when an incident scenario is enabled.",
  "historical_source": {
    "series": "ENR Construction Cost Index, national 20-city average",
    "source_url": "https://www.enr.com/ext/resources/Issues/National_Issues/2026/30-Mar/ENR033026_1QCR_compressed.pdf",
    "source_report_date": "2026-03-30",
    "pdf_page": 12,
    "printed_page": 77,
    "pdf_sha256": "7c3b91af8a89cf76f468fe60b1b1d5d862b6d660318105bc54f90aad07ab63e8",
    "monthly_rows": 264,
    "annual_rows": 22,
    "notes": [
      "Historical values rounded to integers as published in the report.",
      "Not seasonally adjusted; historical values may be revised.",
      "Published 2024 annual average 13571 differs from mean of published rounded monthly values 13564.833; both preserved without correction.",
      "PDF heading contains an inconsistent base label; ratio and growth calculations are invariant to a fixed base rescaling.",
      "This is a March 2026 historical-data vintage, not real-time vintages for each observation."
    ]
  },
  "saved_date": "2026-10-30"
}